| |
Four-plane Hangar
Beijing Plane Maintenance
Engineering Co., ltd
¡¤Floor area: 53,862 m2
¡¤36 months contract duration
¡¤Steel roof 306X95 meters,
the weight is 5,500 tons.
¡¤One 3500 tons steel base of
eastern medium column to
support the roof.
¡¤40m height, no any vertical
column inside.
¡¤The roof is linked by seven
pieces steel structure, which
are lifted by hydraulic jacks
after site assembled.
¡¤
50,000m2 welded seam on
roof, whole procedure
Controlling,
inspection on
each millimeter.
No any leakage till now.
Gate Hoisting
¡¤8 sets of electrical gate and
about 7000 square meters.
Steel structure hoisting
Grid space lifting
A380 Hangar Construction Project
Name of Client: AMECO
Location: Capital Airport
Value: RMB 412.83 Million
Floor Area:64,285 m2
Contract Duration:17 Months
Type of Main Structure
Spacing Truss & spacing Ball Span 2¡Á176.3m¡Á110m
Grid space lifting
Beijing Friendship Hospital New
Emergency Outpatient and Teaching Project
February 2002-February 2004
Hospital Project-Frame Structure
Client: Beijing Friendship Hospital
Turnkey Project
Value: RMB 260,000,000
Building Area: 53,000 sqm
Award: Luban Award and Great Wall
Golden Medal
Schenker BITCC Logistics Center (Beijing) Project
Logistic Center
-Steel and Frame Structure
Client:
Schenker BITCC Logistic Co., Ltd.
Value: RMB 45,084,223
Building Area: 16,870 sqm
Award: Great Wall Award
STMT(Siemens) Building B&D, Beijing
June 2002£Dec 2002
Renovation and Expansion- Frame Structure
Client: Beijing Siemens Technical Management Co,. Ltd. (STMT)
Turnkey
Value: RMB 21,490,000
Building Area: 7,200sqm
Waste Water Treatment Plant
Shijiazhuang (Hebei Province)
Name of Client:
Shijiazhuang Waste Water Treatment
Co., Ltd.
Location:: Shijiazhuang
Value: RMB82,000,000
Contract Duration: 18 Months
Type of Main Structure
Pre stress Concrete Shell Structure
Subway Line 10 Lot 04)
Name of Client:
Beijing Railway Transportation
Construction Management Co., Ltd.
Location: Beijing
Value: RMB223, 000,000
Contract Duration:20 Months
Guangzhou Railway Transportation
Line 6 Lot 3 TBM Works
(Huangsha Station to
Haizhu Square Station)
Name of Client: Guanzhou Subway
Corporation
Location: Guangzhou
Value: RMB 213 Million
Contract Duration30 Months
Beijing Subway Line 10 Phase II Lot 01
Name of Client: Beijing Infrastructure Facility Investment Co., Ltd.
Location: Beijing
Value: RMB 521,107,747
Contract Duration: 23 months
The project includes two stations, one mining TBM tunnel, two TBM tunnel.
The total construction area is 26907.23 m2£¬the mining part has length of 1283m, and total length of two lines of TBM is 1699m.
Capital International
Airport Line Lot 10 Project
(T2 Branch Right Line TBM works)
Name of Client:
Beijing Dongzhimen Airport Speedy
Railway Co., Ltd.
Location: Beijing
Value: RMB 136 Million
Contract Duration21 Months
|
|
 |
|
|
|
Project General Situation
Line Airport Lot10B belongs to Beijing Railway Line Airport
Lateral T2(right line), is an underground lot. The design
jumping-off point mileage of the tunnel is Right T2K1+295,the
end-point is Right T2K5+397, the span is 4102m,shield tunneling
technology is used.
This tunnel earth up 5.7m¡«11.5m, The Maximum Longitudinal Slope
is 4.016¡ë, the minimum turning radius is 550m; the main stratums
are silt clay and silty fine sand stratum; the work area which
has a higher water table is water table aquifer.
The inner diameter of the shield tunnel is 5400mm, and the outside
diameter is 6000mm, prefabricated prestressed concrete segment is
used, which is 30cm thick, 1200mm width. The whole line uses
universal segment lining assembling ,the segments seam in stagger.
Project Schedule
Construction Situation£º
As the work area has handed over on July 19 2006, the project was
shaping up.
The TBM mainframe began to assembling from July 28 2006, there
was an Assemble Rite on August 9th 2006, the cutterhead was carried
into the beginning-well that day.
The excavation began on August 26 2006.
The TBM arrived at the received-well on April 25 2007, the tunnel excavation
was finished. The excavation length is 4092m (3407 rings segments),
which last 243 days, the monthly record is 518.4m. The project was finished
6 months ahead of the owner¡¯s schedule,
From September 20 2006 to October 20 2006, 606 rings ( 727.2m) had
finished, which renewed the monthly record; September 24 2006, the new
daily record was brought out ,which is 35 rings a day.
Assemble the trolley
TBM assembling
Cutterhead Assembled Rite, August 9th 2006
TBM cutterhead assembled
The first pipe of soil poured into the disposal area, night, August 26 2006
The first step of excavation was finished on Sep 14 2006£¬the excavation began again on Sep 20 2006
The excavation has finished about 1530m, 1266rings, the TBM reached and began to go through the No. 1 wind tunnel, November 12 2006.
The TBM has already went through the No. 1 wind tunnel, began to excavate the second tunnel on November 19,2006
2800m(2335rings) has already finished on Feb 2nd 2007, the TBM reached and began to go through the No.2 wind tunnel
The TBM has already went through the No.2 wind tunnel on Feb 20 2007, and began the excavation of the last tunnel
The TBM reached the receive-well, the whole tunnel was run-through on April 25 2007, the excavation length is 4092m (3407rings)
Night, May 1st 2007, a 385t crane and a 220t crane assembled, the day after the TBM began to disassemble, two days later the TBM disassembly finished
The TBM disassembly
The trolley transported out
Subway Line 9 Lot 2
Name of Client: Beijing Railway
Transportation Construction
Management Co., Ltd.
Location: Beijing
Value: RMB 420,855,375
Contract Duration: 1310 Calendar Days
The project includes two stations and three tunnels. Total construction area of stations is 27382.83m2. The total length of double lines is 2428.55m.
October
1996 - December 1998
Residential Project
Client: Beijing Oulu Property
Development Co., Ltd.
Turnkey
Value: RMB 270,000,000
Building Area: 35,600 sqm
97 Villa Buildings, Clubhouse
and M+E Buildings
Beijing Eurovillage
October 1997 - June 1998
Industrial Building
Client: Bayer Guangyi Panel
Co., Ltd.
Turnkey
Value: RMB 27,200,000
Building
Area: 6,136 sqm
Beijing Bayer Guangyi Panel
Factory
April 1998 - November 1998
Commercial Building
Client: CTA Makro Commercial
Co., Ltd.
Turnkey
Value:
RMB 56,800,000
Building
Area: 35,269 sqm
CTA Makro Jiuxianqiao
Store, Beijing
Since 1998
Conceptual Design
Client: AUDI AG Germany
Value:
RMB 3,440,000
Scope: 82 showrooms all over
China
Audi Showroom
October 1999 - January 2000
Research Building
Client: Beijing Zoo
Turnkey including design
Value:
RMB 3,225,000
Building
Area: 689 sqm
Panda
Research Center, Beijing
January 2000 - December
2000
Research and Manufacture Building
Client: Beijing International
Switching System Corp. Ltd.
Turnkey
Value:
RMB 52,360,000
Building
Area: 16,204 sqm
Beijing International Switching
System (BISC)
July 2000 - October 2000
Client: Volkswagen (China) Investment
Co. Ltd.
Construction, Design, Architectural
and M+E Finishing Works
Value:
RMB 8,060,000
Building
Area: 980 sqm
Volkswagen Auto Forum, Beijing
October 2000 - September
2001
Renovation and Expansion
Client: Beijing Siemens Technical
Management Training Co., Ltd. (STMT)
Turnkey Project
Value:
RMB 17,599,000
Building Area: 4,100 sqm
SLC (Siemens) Head Office, Beijing
August 2001 - January 2002
Client: Beijing Better Life
Automobile Import / Export Co., Ltd.
Turnkey Project
Value:
RMB 9,230,000
Building Area: 5,280 sqm
Beijing Better Life Audi Showroom
February 2002 - February
2004
Client: Beijing Friendship Hospital
Turnkey Project
Value:
RMB 260,000,000
Building
Area: 52,000 sqm
Beijing Friendship Hospital
February 2002 - September
2002
Commercial Building Extension
Client: Beijing (Siemens) BITCC
Turnkey Project
Value:
RMB 4,630,000
Building Area: 757 sqm
Beijing BITCC Multifunction
Hall
April 2002 - Mar 2003
Industrial Building
Client: Kurz Stamping Technology
(Hefei) Co., Ltd.
Turnkey Project
Value:
RMB 50,007,000
Building
Area: 18,000 sqm
Kurz Stamping Factory, Hefei
(Anhui Province)
May 2002 - September 2003
Industrial Building
Client: HÖrmann
Beijing Door Production Co., Ltd.
Building
Works, External Works
Value:
RMB 3,700,000
Building Area: 7,500 sqm
HÖrmann Beijing Door Production
Phase II
June 2002 - December 2002
Renovation and Expansion
Client: Beijing Siemens Technical
Management Training Co., Ltd. (STMT)
Turnkey Project
Value:
RMB 21,490,000
Building Area: 7,200 sqm
STMT (Siemens) Building B £¦
D, Beijing
Contract awarded December
28,2002
Finishing date: December 28,2005
Infrastructure Project
Client: Beijing Mass Transit
Railway (Group) Corp. Ltd.
Tunnel Works with TBM
Value:
RMB 105,613,161
Scope: 2,800 m tunnel works
Beijing Subway Line 5, Lot 17
May 2003 - December 2003
Porsche Showroom £¦ Audi Used
Car Showroom
Beijing
Development Area
Client: Beijing Better Life
Automolile Import / Export Co., Ltd
Turnkey Project
Value:
RMB 4,500,000
Porsche Showroom £¦ Audi Used
Car Showroom
Since June 2003 Flender
Tianjin "Investment Phase II" Project
Tianjin
Client: Flender Power Transmission
Co., Ltd.
Turnkey Project
Value:
RMB 13,600,000
Building
Area: 6,000 sqm
December 2003 - December
2005
Beijing
Subway Line 10 Lot 5-Zhi Chun Lu Station Project
Beijing
Client: Beijing Mass Transit
Railway (Group) Corp. Ltd.
Value:
RMB 123,110,000
Building
Area: 11,468 sqm
Scope: 172.2m station and tunnel
works
Further Projects :
February 2003 - March 2003 LBC (MAN) Factory
Project
Zhengzhou (Henan Province)
Consultancy Services
Client: Lion Bus Co., Ltd.
June 1998 - March 1999 P£¦G
Whisper Factory Expansion
Client: P£¦G Manufacturing (Tianjin)
Co., Ltd.
Value:
RMB 27,854,730
Building
Area: 26,507 sqm
1999 Effem Foods (Beijing)
Factory Expansion
Client: Effem Foods (Beijing)
Co., Ltd.
Value: RMB 5,121,162
Building Area: 4,430 sqm
|